April 3, 2015 - Foundation walls are up.



 April 11, 2015 - Underground plumbing is installed.


April 15, 2015 - Framing is beginning and beams are installed.



April 21, 2015 - Framing of 1st and 2nd floor is complete.



May 2, 2015 - Basement is framed, HVAC is beginning to be installed, walk out basement sliding glass door is installed.







 May 9, 2015 - HVAC, plumbing, and electrical have all been installed.  Also, the bathtub and rest of the furnace and Guardian ethernet things.
 Morning room portion of the basement.

 Looking out of the bathroom.

 The standard tub and shower combination.


 Furnace with wires and plumbing and such.
May 16, 2015 - Insulation was installed and sheet rock was being put up.

  Morning Room portion.
May 19, 2015 - Sheet rock has been put on most walls.



 May 23, 2015 - All sheet rock is up and dry wall is in progress.



 May 30, 2015 - Dry wall is complete, ceilings complete, primer was being put on today.


 June 6, 2015 - Walls were painted, baseboards were installed, some doors were installed, bathroom vanity and lights were installed, balusters were installed.







 June 13, 2015 - Toilet and mirror installed in basement, water tank installed, dry wall touch ups, dry handles installed, faucets installed.




June 20, 2015 - Carpet was installed, railings were stained