April 21, 2015 - Framing of the 1st and most of 2nd floor have been completed.
 April 25, 2015 - Windows are installed.


 
May 2, 2015 - Patio door is installed.



May 9, 2015 - Room has been cleaned out, light "rough in" has been installed, and electrical has been installed.


 I can't get over how high up this ceiling is!

 May 16, 2015 - Insulation was installed, sheet rock is going up.


 May 19, 2015 - Sheet rock installed, in the process of dry wall.


 May 23, 2015 - More progress on the dry wall.
 May 30, 2015 -Dry wall is complete, ceiling is complete, primer was being painted on today.

 June 6, 2015 - Walls were painted, baseboards and windowsills were installed, flooring was going in today.


June 13, 2015 - Drywall is being touched up, vinyl flooring is installed.

 