Outdoor Progression Photos


March 22, 2015 
 
Lot being prepared for excavation.
March 27, 2015
The hole for the foundation of the home was halfway done.
What it looked like from the street.
March 29, 2015
The hole was completely finished.
March 30, 2015
The footers were poured.
The footers were poured.
April 3, 2015
The foundation walls are up.
The foundation walls are up.
April 11, 2015
 The underground plumbing is installed.

April 15, 2015
The framing of the first floor has begun.
The framing of the first floor has begun.

April 21, 2015
The first two floors have and are being framed.
April 25, 2015
The framing is compete and the windows are installed.
May 2, 2015
 We have a roof, slab poured, and HVAC being installed.  And that little circle thing at the top.
May 9, 2015
HVAC, electrical, plumbing have all been installed.  Another hole was dug on the right front side of the house.
 Top far right corner are the wires for one of our flood lights.
 Top corner are the other wires for our second flood light.
 More things poked out of the side of the house.
 Large hole dug on the right side of the house.
May 11, 2015 - Part of the garage doors were installed and we got a casing around the front door.


 May 14, 2015 - Insulation is being installed
 May 19, 2015 - Brick was delivered, dry wall is in the process of being put up.

  May 23, 2015 - The brick is in the process of being put up.


 May 30, 2015 - Brick finished all around the house, dry wall is complete, beginning of primer.







 June 6, 2015 - Siding was put on, shutters were put on, trim was put on, outdoor lights were added, and the garage doors were installed.  As for inside, the paint is done, the trim is up, some doors are installed, kitchen cabinets and vanities are installed, counter tops are in, balusters were installed and stained, and the flooring was going in today.



 June 13, 2015 - Siding complete, lights by front door installed, starting to clean up the yard.




 June 20, 2015 - Door was painted black, screens were added, grading has begun, outdoor light was installed where the sidewalk will be, gutters were added, carpet was installed.






 